Under construction

BALAJI VIVANTA

by MAYUR ENTERPRISES BUILDERS & DEVELOPERS

PLOT NO 3 ,HISSA NO 1 ,2,3 ,4 OLD SURVEY NO 71 HISSA NO 1,2,3,4 NEW SURVEY NO 4 HISSA NO 1, OLD SURVEY NO 72 HISSA NO 1, KALYAN, 421103

Dec 2023
Possession
13.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 13.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P51700029805
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
13.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings17%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space20%

Building & registration

RERA registered
Jul 2021
Floors
9

Buyer community

Connect with other buyers and owners of BALAJI VIVANTA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BALAJI VIVANTA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.