PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Riverwood Park Building No -3

by Shree Khidkaleshwar Property Developers Pvt. Ltd.

26/2, 26/3 all in Parts, Sagarli, Dombivili East, 421204

Jun 2027
Possession
82.7%
Built
0
Complaints
159
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51700030195
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2026
Construction
82.7% complete
Units sold
140 of 159

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains30%
Landscaping & Tree Plantingnot started
Street Lighting20%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirements35%
Electrical meter room, sub-station, receiving station20%

Building & registration

RERA registered
Aug 2021
Floors
28
Unit mix
159 res ยท 0 comm
Architect
Vasturachna

Buyer community

Connect with other buyers and owners of Riverwood Park Building No -3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Riverwood Park Building No -3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.