Aug 2026
Possession
72.7%
Built
0
Complaints
142
Units
Caution
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Aug 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700030327
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2026originally December 2024
- Construction
- 72.7% complete
- Units sold
- 122 of 142
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2021
- Floors
- 14
- Unit mix
- 130 res ยท 12 comm
Buyer community
Connect with other buyers and owners of AVIGHNA KARAN WING C โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AVIGHNA KARAN WING C. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.