MADHUSUDAN RETREATMahaRERA P51700030973

by MADHUSUDAN LEISURE HOMES

CTS PLOT BEARING NO 50, THANE, 421401

Mar 2027
Possession
14.4%
Built
0
Complaints
106
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 14.4%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700030973
Status
New
Stage
Certificate Signed
Possession
March 2027originally June 2024
Construction
14.4% complete
Units sold
52 of 106

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started

Building & registration

RERA registered
Sept 2021
Floors
3
Unit mix
53 res ยท 0 comm
Architect
ASHISH AGARWAL

Buyer community

Connect with other buyers and owners of MADHUSUDAN RETREAT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MADHUSUDAN RETREAT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.