Under construction

AVASAR PRIDE

by D P REALTY

Survey No. 44, Hissa no. 2, Mouje Village, 421204

Dec 2026
Possession
10.9%
Built
0
Complaints
87
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 10.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700031454
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
10.9% complete
Units sold
0 of 87

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2021
Floors
7
Unit mix
77 res ยท 10 comm
Architect
The Firm

Buyer community

Connect with other buyers and owners of AVASAR PRIDE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AVASAR PRIDE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.