Under construction

N G AROMA PHASE II

by RNA Builders (NG)

S. No. 250 Old / S. No. 46 NEW, NAVGHAR, 401107

Dec 2026
Possession
9.1%
Built
1
Complaints
42
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 9.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700032464
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
9.1% complete
Units sold
41 of 42

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2022
Floors
9
Unit mix
42 res ยท 0 comm

Buyer community

Connect with other buyers and owners of N G AROMA PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching N G AROMA PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.