PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Regency Antilia Phase VII

by REGENCY NIRMAN LTD

Survey No. 40, 41, 42, 43, 44, 46, 47, 48, 49, 50, 51, 52, 54, 55, 56, 57, 58, Mharal, 421001

Sept 2025
Possession
82.7%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 82.7%.

Official RERA facts

Registration
P51700032863
Status
New
Stage
Certificate Signed
Possession
September 2025originally March 2025
Construction
82.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lighting50%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal65%
Water conservation /Rain water harvesting50%
Energy managemcnt55%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacedone
Open Parkingnot started

Building & registration

RERA registered
Feb 2022
Floors
34

Buyer community

Connect with other buyers and owners of Regency Antilia Phase VII โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Regency Antilia Phase VII. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.