Under construction

Tulsi Galaxy

by Manas Associates

S No 69 H No 16, S No 69 H No.17, S no. 69 H No. 17P B, S No. 51, H No.5, NA, 421501

Mar 2027
Possession
0%
Built
0
Complaints
354
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700033355
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2025
Construction
0% complete
Units sold
162 of 354

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2022
Floors
9
Unit mix
354 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Tulsi Galaxy โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Tulsi Galaxy. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.