PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

BALAJI RAGHAV

by STAR GROUP

S NO 78 HISSA NO 4/1/B, DOMBIVALI EAST, 421201

Dec 2027
Possession
0%
Built
0
Complaints
0
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51700033628
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Mar 2022
Floors
9

Buyer community

Connect with other buyers and owners of BALAJI RAGHAV โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BALAJI RAGHAV. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.