Under construction

KALYAN VIHAR

by HONEST DEVELOPERS

SURVEY NO 188 H NO 5/E11, 17/A,18/B ILLAGE KON, BHIWANDI, 421302

Dec 2029
Possession
60.2%
Built
0
Complaints
105
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2026, now proposed Dec 2029 per the RERA filing.

Official RERA facts

Registration
P51700033988
Status
New
Stage
Certificate Signed
Possession
December 2029originally March 2026
Construction
60.2% complete
Units sold
69 of 105

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains30%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parking50%

Building & registration

RERA registered
Mar 2022
Floors
24
Unit mix
101 res ยท 4 comm
Architect
K K AND ASSOCIATES

Buyer community

Connect with other buyers and owners of KALYAN VIHAR โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KALYAN VIHAR. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.