SAI WORLD
SURVEY NO 181 H NO 2/3/4/A, BORADPADA ROAD, 421503
Mar 2026
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 90.9%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700034155
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2026
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Mar 2022
- Floors
- 9
Buyer community
Connect with other buyers and owners of SAI WORLD โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAI WORLD. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.