Under construction

KALYAN RESIDENCY

by SM LIFE SPACE PRIVATE LIMITED

SURVEY NO 185 H NO 15& S NO 281 H NO 1,2,3 & 4 VILLAGE KON, BHIWANDI, 421302

Dec 2028
Possession
65.1%
Built
0
Complaints
96
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2025, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51700034384
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2025
Construction
65.1% complete
Units sold
74 of 96

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths75%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Apr 2022
Floors
21
Unit mix
91 res ยท 5 comm
Architect
K K AND ASSOCIATES

Buyer community

Connect with other buyers and owners of KALYAN RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KALYAN RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.