Under construction

PEARL A

by LODHA DEVELOPERS LIMITED

29/1A/1 (P), 29/1B/1 (P), 29/1B/2 (P), 29/1/2 (P), 29/5A (P) & 29/5B (P), Kalyan, 421204

Dec 2025
Possession
81.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 81.8%.

Official RERA facts

Registration
P51700034753
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingnot started

Building & registration

RERA registered
Apr 2022
Floors
14

Buyer community

Connect with other buyers and owners of PEARL A โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PEARL A. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.