Under construction

FATIMA ENCLAVE- C WING

by RAIS AZIZ QURESHI

46/4 , 46/5, KAUSA, 400612

Mar 2027
Possession
64.1%
Built
0
Complaints
113
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700035020
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2025
Construction
64.1% complete
Units sold
60 of 113

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2022
Floors
20
Unit mix
107 res ยท 6 comm
Architect
ANWAY VINAY PATIL

Buyer community

Connect with other buyers and owners of FATIMA ENCLAVE- C WING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FATIMA ENCLAVE- C WING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.