Under construction

MADHUSUDAN BUILDING

by MADHUSUDAN BUILDCON

PLOT NO. 138, CTS NOS. 3918 TO 3924, KANSAI SECTION, 421501

Dec 2026
Possession
17%
Built
0
Complaints
13
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 17%.
Ambernath / BadlapurValue

The value frontier beyond Kalyan โ€” low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700035033
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
17% complete
Units sold
0 of 13

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drains25%
Open Parking50%

Building & registration

RERA registered
Apr 2022
Floors
8
Unit mix
12 res ยท 1 comm
Architect
MANOHAR M WALIMBE

Buyer community

Connect with other buyers and owners of MADHUSUDAN BUILDING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MADHUSUDAN BUILDING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.