Under construction

Radhe Govind Commercial Complex

by Shree Radha Construction

Gut No.59 (P),(C.T.S.No.9004), Morivali Ambarnath, 421501

Dec 2026
Possession
28.2%
Built
0
Complaints
40
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 28.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Ambernath / BadlapurValue

The value frontier beyond Kalyan โ€” low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700045967
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
28.2% complete
Units sold
4 of 40

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2022
Floors
8
Unit mix
0 res ยท 40 comm
Architect
Satish Kanade

Buyer community

Connect with other buyers and owners of Radhe Govind Commercial Complex โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Radhe Govind Commercial Complex. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.