Under construction

Omkar Residency A-Wing

by K K GROUP

S.No 2/5/B, Bhiwandi, 421302

Dec 2026
Possession
44.1%
Built
0
Complaints
36
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 44.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700046189
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
44.1% complete
Units sold
21 of 36

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2022
Floors
9
Unit mix
28 res ยท 8 comm
Architect
PMC MASTERS

Buyer community

Connect with other buyers and owners of Omkar Residency A-Wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Omkar Residency A-Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.