No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P51700046381
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally May 2026
- Construction
- 98.2% complete
- Units sold
- 64 of 102
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 20 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting90%
Street Lighting90%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal90%
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station95%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Jun 2022
- Floors
- 38
- Unit mix
- 102 res ยท 0 comm
Buyer community
Connect with other buyers and owners of REGENCY PALMS PHASE IV โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching REGENCY PALMS PHASE IV. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.