RITZ TOWER B

by VIKAS HARAKCHAND JAIN

6/1/3, 6/2, 39/1/1 (Part), 39/5, SHREE COMPLEX PHASE III, 421301

Sept 2026
Possession
42.7%
Built
0
Complaints
145
Units
High risk
  • Behind schedule. Possession is due Sept 2026 but construction is only at 42.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700047353
Status
New
Stage
Certificate Signed
Possession
September 2026
Construction
42.7% complete
Units sold
135 of 145

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2022
Floors
30
Unit mix
145 res · 0 comm
Architect
Vitan Consultants

Buyer community

Connect with other buyers and owners of RITZ TOWER B — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching RITZ TOWER B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.