Under construction

SHIVANAND SRA CHS

by MADHUR MANOHAR RAO

S. no. 378 , CTS No. 1333 (Rt), Thane, 400605

High risk
  • Possession delayed ~2 yrs. Originally promised May 2025, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 37.2%.
  • Promised amenities not started. Gymnasium, Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700047399
Status
New
Stage
Certificate Signed
Possession
December 2026originally May 2025
Construction
37.2% complete
Units sold
0 of 0

RERA complaint record3 records

  • ComplaintCC1260218714 Apr 2026
    Mahesh Vasudev Takke vs MADHUR MANOHAR RAO
  • ComplaintCC1250296822 Aug 2025
    SHIVARAM MANOHAR RAUL vs MADHUR MANOHAR RAO
  • ComplaintCC1250296722 Aug 2025
    SHIVARAM MANOHAR RAUL vs MADHUR MANOHAR RAO

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Welfare Hallnot started
Society Officenot started
Librarynot started
Gymnasiumnot started
Balwadinot started

Building & registration

RERA registered
Oct 2022
Floors
22

Buyer community

Connect with other buyers and owners of SHIVANAND SRA CHS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIVANAND SRA CHS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.