All RERA projects
๐๏ธ
Under construction
OM AVENUE
by M/S SHREE SWAMI SAMARTH ENTERPRISES
SURVEY NO. 75, HISSA NO. 2/2/1 B/2, WADEGHAR VILLAGE, 421301
Dec 2026
Possession
78.2%
Built
0
Complaints
27
Units
Caution
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700048509
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 78.2% complete
- Units sold
- 20 of 27
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drains20%
Landscaping & Tree Planting10%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements25%
Electrical meter room, sub-station, receiving station40%
Building & registration
- RERA registered
- Jan 2023
- Floors
- 12
- Unit mix
- 22 res ยท 5 comm
- Architect
- EMERGE ARCHITECTS & ASSOCIATES
Buyer community
Connect with other buyers and owners of OM AVENUE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching OM AVENUE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.