Under construction

M/S V.K.CONSTRUCTIONS

by VIKRAM RAMESH KATHOLE

S.NO 168/5/1/A, VASIND, 421601

Dec 2026
Possession
43.6%
Built
0
Complaints
64
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700049629
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
43.6% complete
Units sold
20 of 64

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parking12%

Building & registration

RERA registered
Feb 2023
Floors
7
Unit mix
64 res ยท 0 comm
Architect
ADEEB KHOT

Buyer community

Connect with other buyers and owners of M/S V.K.CONSTRUCTIONS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching M/S V.K.CONSTRUCTIONS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.