Dec 2031
Possession
39.8%
Built
0
Complaints
118
Units
Caution
- Possession delayed ~3 yrs. Originally promised Dec 2028, now proposed Dec 2031 per the RERA filing.
Official RERA facts
- Registration
- P51700049697
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2031originally December 2028
- Construction
- 39.8% complete
- Units sold
- 3 of 118
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths30%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Feb 2023
- Floors
- 12
- Unit mix
- 108 res ยท 10 comm
- Architect
- JOSHI DESHAWARE & ASSOCIATES
Buyer community
Connect with other buyers and owners of MM VALLEY D1 D2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MM VALLEY D1 D2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.