PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ASHWIN KIRTI CO-OP HSG SOCIETY

by VINAYAK ENTERPRISES DEVELOPERS

S.No.17,H.No.3,Plot No.1, VILLAGE SHIRGAON BADLAPUR, 421503

Jun 2024
Possession
81.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 81.8%.

Official RERA facts

Registration
P51700049734
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Storm Water Drainsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Feb 2023
Floors
7

Buyer community

Connect with other buyers and owners of ASHWIN KIRTI CO-OP HSG SOCIETY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ASHWIN KIRTI CO-OP HSG SOCIETY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.