NASCON MATOSHREE

by OMKAR DEVELOPERS

2105 TO 2110, Navagaon Dombivli East, 421202

Dec 2026
Possession
41.4%
Built
0
Complaints
54
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 41.4%.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700049858
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
41.4% complete
Units sold
10 of 54

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2023
Floors
19
Unit mix
29 res · 25 comm
Architect
Sarvesh B Nandgirikar

Buyer community

Connect with other buyers and owners of NASCON MATOSHREE — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching NASCON MATOSHREE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.