All RERA projects
๐๏ธ
Under construction
Vedant Millenia happiness Phase II Wing C
221/3/1 (P).221/3/2 (P),221/4 (P),221/6A (P), Kalyan, 421605
Dec 2027
Possession
45.5%
Built
1
Complaints
197
Units
Caution
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700050205
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 45.5% complete
- Units sold
- 95 of 197
RERA complaint record1 record
- ComplaintSM126000319 Jan 2026Bhakti Achrekar vs MOHAN HARDASMAL THARWANISM12600030 31 32 33 34 Draft Order.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Mar 2023
- Floors
- 26
- Unit mix
- 197 res ยท 0 comm
- Architect
- ARCHITECTS INC
Buyer community
Connect with other buyers and owners of Vedant Millenia happiness Phase II Wing C โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Vedant Millenia happiness Phase II Wing C. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.