Under construction

Shri Sai Mangal Co-Op Housing Society Ltd A Building

by AMOGH ASSOCIATES

Plot No 26, Bearing Old Survey No 212, Hissa No 5 Part, New Survey No 9, H No 5 Part, Village Chole , Thakurli, 421201

Dec 2025
Possession
84.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 84.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P51700050524
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
84.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2023
Floors
8

Buyer community

Connect with other buyers and owners of Shri Sai Mangal Co-Op Housing Society Ltd A Building โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shri Sai Mangal Co-Op Housing Society Ltd A Building. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.