PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Tulsi Vrundavan

by Tulsi Builders and Developers

Gut No.13 & 14, Near Vangani Railway Station, 421503

Sept 2026
Possession
61%
Built
0
Complaints
287
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P51700051177
Status
New
Stage
Certificate Signed
Possession
September 2026
Construction
61% complete
Units sold
152 of 287

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2023
Floors
8
Unit mix
287 res ยท 0 comm
Architect
Raj Associates (Ar. S R Khambayat)

Buyer community

Connect with other buyers and owners of Tulsi Vrundavan โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Tulsi Vrundavan. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.