Under construction

Mellennium Dreams

by Mellennium Dreams

Plot No 45 46 54 and 55 (part), Old Survey No 326/A part New Survey No 229 part, Dombivli, 421202

Mar 2027
Possession
70.9%
Built
0
Complaints
97
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700051350
Status
New
Stage
Certificate Signed
Possession
March 2027originally May 2026
Construction
70.9% complete
Units sold
25 of 97

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2023
Floors
14
Unit mix
89 res ยท 8 comm
Architect
Rachana Shilp

Buyer community

Connect with other buyers and owners of Mellennium Dreams โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Mellennium Dreams. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.