Under construction

CHANGUNA AANGAN

by SAMRIN DREAMSPACES PRIVATE LTD

S. NO. 162 & 167 H. NO. 4, S. NO. 162 & 167 H. NO. 4, 400612

Jun 2027
Possession
37.5%
Built
0
Complaints
353
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Jun 2027 per the RERA filing.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 37.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51700051386
Status
New
Stage
Certificate Signed
Possession
June 2027originally December 2025
Construction
37.5% complete
Units sold
102 of 353

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2023
Floors
20
Unit mix
337 res ยท 16 comm

Buyer community

Connect with other buyers and owners of CHANGUNA AANGAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching CHANGUNA AANGAN. Real notes from real buyers beat any brochure.

Start a discussion