SAGAR HEIGHTS

by AADINATH DEVELOPERS

SURVEY NO. 61/3/1 / NEW CTS NO. 729/A , 734/A, KHADAKPADA, 421301

Jun 2026
Possession
90.5%
Built
0
Complaints
101
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 90.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51700051990
Status
New
Stage
Certificate Signed
Possession
June 2026originally December 2025
Construction
90.5% complete
Units sold
25 of 101

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drains85%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting75%
Fire protection and fire safety requirements90%

Building & registration

RERA registered
Jul 2023
Floors
23
Unit mix
97 res · 4 comm
Architect
VITAN CONSULTANTS

Buyer community

Connect with other buyers and owners of SAGAR HEIGHTS — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SAGAR HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.