Under construction

COSMOS ENCLAVE BLDG-JASMINE

by MONARCH DEVELOPERS

9/3 A, 3b, 13/1A & 1B, 3/1A & 3/1B, 13/2, KASARVADAVLI, THANE WEST, 400615

Dec 2026
Possession
85.5%
Built
0
Complaints
164
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700052301
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
85.5% complete
Units sold
74 of 164

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting50%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2023
Floors
21
Unit mix
154 res ยท 10 comm
Architect
Suvarna Ghosh

Buyer community

Connect with other buyers and owners of COSMOS ENCLAVE BLDG-JASMINE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching COSMOS ENCLAVE BLDG-JASMINE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.