PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Fiora K

by Fiora K

24/1A Part,24/1B Part,260/1A Part,260/1B Part, Kalyan, 421203

Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700052406
Status
New
Stage
Certificate Signed
Possession
January 2028
Construction
72.2% complete
Units sold
86 of 161

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drains75%
Landscaping & Tree Planting60%
Street Lighting65%
Community Buildings40%
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal60%
Water conservation /Rain water harvesting60%
Energy managemcnt50%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space50%
Open Parking60%

Building & registration

RERA registered
Aug 2023
Floors
24
Unit mix
161 res ยท 0 comm
Architect
Pradeep Kamble

Buyer community

Connect with other buyers and owners of Fiora K โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Fiora K. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.