Under construction

Runwal Gardens Phase 8 Bldg No. 43 and 45

by Runwal Residency Private Limited

Old Survey no. 44/15 (pt), 44/19 (pt), New Survey no. 4/B/20(pt), Dombivali, 421204

Sept 2028
Possession
31.7%
Built
2
Complaints
248
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2026, now proposed Sept 2028 per the RERA filing.

Official RERA facts

Registration
P51700052441
Status
New
Stage
Certificate Signed
Possession
September 2028originally December 2026
Construction
31.7% complete
Units sold
151 of 248

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2023
Floors
36
Unit mix
248 res ยท 0 comm
Architect
Saakar Architects

Buyer community

Connect with other buyers and owners of Runwal Gardens Phase 8 Bldg No. 43 and 45 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Runwal Gardens Phase 8 Bldg No. 43 and 45. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.