Under construction

BELPATRA

by MAHADEV DEVELOPERS

SURVEY NO 95 HISSA NO 2 (PT),MAUJE BAPGAON,BHIWANDI, BHIWANDI, 421302

Sept 2027
Possession
64.2%
Built
0
Complaints
100
Units
High risk
  • Possession delayed ~1 yr. Originally promised May 2026, now proposed Sept 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.

Official RERA facts

Registration
P51700053122
Status
New
Stage
Certificate Signed
Possession
September 2027originally May 2026
Construction
64.2% complete
Units sold
27 of 100

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2023
Floors
12
Unit mix
81 res ยท 19 comm
Architect
GEO ASSOCIATES

Buyer community

Connect with other buyers and owners of BELPATRA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BELPATRA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.