Rameshwar Co-Op Housing Society Ltd.
Final Plot no 327 of T.P.S. No. 1, Panchpakhadi, Thane West, 400602
- Behind schedule. Possession is due Mar 2027 but construction is only at 40.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
A full city of its own โ lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51700053476
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027
- Construction
- 40.3% complete
- Units sold
- 8 of 69
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Nov 2023
- Floors
- 15
- Unit mix
- 63 res ยท 6 comm
- Architect
- Saakaar
Buyer community
Connect with other buyers and owners of Rameshwar Co-Op Housing Society Ltd. โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Rameshwar Co-Op Housing Society Ltd.. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.