PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

AYODHYA

by INFINI DEVELOPERS

133/3, 133/4, 134/5, 134/10, 134/11, 138/13/A, 138/13/B, 138/13/C, Temghar, 421302

Mar 2027
Possession
90.9%
Built
0
Complaints
153
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700053968
Status
New
Stage
Certificate Signed
Possession
March 2027
Construction
90.9% complete
Units sold
92 of 153

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Dec 2023
Floors
19
Unit mix
136 res ยท 17 comm
Architect
R K Associates

Buyer community

Connect with other buyers and owners of AYODHYA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AYODHYA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.