PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAI NIDA APARTMENT

by PRASHANT WAGAJI GAWANDE

217 HISSA NO 2(P), BHIWANDI, 421302

Dec 2026
Possession
36.4%
Built
0
Complaints
35
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 36.4%.

Official RERA facts

Registration
P51700054040
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
36.4% complete
Units sold
10 of 35

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Street Lightingnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2023
Floors
7
Unit mix
30 res ยท 5 comm
Architect
A K AND ASSOCIATES

Buyer community

Connect with other buyers and owners of SAI NIDA APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI NIDA APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.