PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Vivanta S Bliss C Wing

by JAI BHAWANI ORCHID INFRA LLP

53/5, 53/6, 310/2, 310/3, & 310/4, Jai Mata di Compound, 421302

Aug 2024
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2024 per the RERA filing.

Official RERA facts

Registration
P51700054239
Status
New
Stage
Certificate Signed
Possession
August 2024originally August 2023
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvesting80%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2024
Floors
8

Buyer community

Connect with other buyers and owners of Vivanta S Bliss C Wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vivanta S Bliss C Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.