Dec 2026
Possession
77.7%
Built
1
Complaints
93
Units
Caution
- Possession delayed ~1 yr. Originally promised Jul 2025, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51700055096
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally July 2025
- Construction
- 77.7% complete
- Units sold
- 53 of 93
RERA complaint record1 record
- ComplaintCC1260023513 Jan 2026Vijay Badriprasad Rajbhar vs MALI INFRA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Feb 2024
- Floors
- 8
- Unit mix
- 87 res ยท 6 comm
- Architect
- MADAN GADGIL Gadgil
Buyer community
Connect with other buyers and owners of Mali Avenue โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Mali Avenue. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.