Under construction

Kamdhenu 23 West Grande

by Kamdhenu 23 West Grande

Plot No-A-12, A-13 and W-192 (D), Thane, 400709

Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700055502
Status
New
Stage
Certificate Signed
Possession
December 2028
Construction
51.6% complete
Units sold
372 of 1008

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2024
Floors
28
Unit mix
0 res ยท 1008 comm
Architect
Soyuz Talib Architects

Buyer community

Connect with other buyers and owners of Kamdhenu 23 West Grande โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kamdhenu 23 West Grande. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.