PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Swarajya

by SAILAVKIK REALTY PRIVATE LIMITED

303,304/1,304/2,304/3,305 TIKKA NO. 13 SECTOR NO. 2, CHARAI, 400601

Mar 2027
Possession
30%
Built
0
Complaints
55
Units
High risk
  • Behind schedule. Possession is due Mar 2027 but construction is only at 30%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51700055753
Status
New
Stage
Certificate Signed
Possession
March 2027
Construction
30% complete
Units sold
10 of 55

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2024
Floors
10
Unit mix
52 res ยท 3 comm
Architect
Ambiaance Design Pvt Ltd

Buyer community

Connect with other buyers and owners of Swarajya โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Swarajya. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.