PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHREE HILL RESIDENCY

by SADGURU CORPORATION

S. NO. 76, HISSA NO. 11,12(PT),13,18 & 19 PLOT NO. A, AMBERNATH, 421503

Mar 2027
Possession
43.6%
Built
0
Complaints
30
Units
Caution
  • Behind schedule. Possession is due Mar 2027 but construction is only at 43.6%.

Official RERA facts

Registration
P51700055920
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
43.6% complete
Units sold
6 of 30

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2024
Floors
8
Unit mix
30 res ยท 0 comm
Architect
Hemant Vaidya

Buyer community

Connect with other buyers and owners of SHREE HILL RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREE HILL RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.