Under construction

RIVERA HOMESMahaRERA P51700056073

by KHUSHI DEVELOPERS

Survey no. 84/3, 84/4/B, 84/2/B/84/4/C/4, SHAHAPUR, 421601

Dec 2028
Possession
63.2%
Built
0
Complaints
91
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700056073
Status
New
Stage
Certificate Signed
Possession
December 2028
Construction
63.2% complete
Units sold
45 of 91

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting10%
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station20%
Open Parkingnot started

Building & registration

RERA registered
May 2024
Floors
8
Unit mix
84 res ยท 7 comm
Architect
MAK DESIGN & CO

Buyer community

Connect with other buyers and owners of RIVERA HOMES โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RIVERA HOMES. Real notes from real buyers beat any brochure.

Start a discussion