PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Haware Palms Kalyan Phase 1MahaRERA P51700056190

by Haware Properties LLP

Survey No.-1 Hissa No.-6, Muthaval Village, 421302

Dec 2028
Possession
41.4%
Built
1
Complaints
178
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700056190
Status
New
Stage
Certificate Signed
Possession
December 2028
Construction
41.4% complete
Units sold
119 of 178

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
May 2024
Floors
8
Unit mix
162 res ยท 16 comm
Architect
PB Associates

Buyer community

Connect with other buyers and owners of Haware Palms Kalyan Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Haware Palms Kalyan Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.