Under construction

NEW VANRAI PARAG CHSMahaRERA P51700056295

by VINAYAK ENTERPRISES

NEW SURVEY NO 93/1/A MOUJE KATRAP, KULGAON, 421503

Dec 2026
Possession
53.2%
Built
0
Complaints
73
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700056295
Status
New
Stage
Certificate Signed
Possession
December 2026originally May 2026
Construction
53.2% complete
Units sold
23 of 73

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
May 2024
Floors
28
Unit mix
55 res ยท 18 comm
Architect
RAJ ASSOCIATES

Buyer community

Connect with other buyers and owners of NEW VANRAI PARAG CHS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NEW VANRAI PARAG CHS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.