Under construction

SHIV PRARAMBHMahaRERA P51700066515

by shivaditya realty llp

S.N. 33, old S.N. 123/1(P), H.N. 1/3, 1/D, CTS No. 1139 & 1141(P), Dombivli, 421201

Jun 2027
Possession
44.5%
Built
0
Complaints
13
Units
High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 44.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51700066515
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2026
Construction
44.5% complete
Units sold
7 of 13

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2024
Floors
6
Unit mix
10 res ยท 3 comm

Buyer community

Connect with other buyers and owners of SHIV PRARAMBH โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIV PRARAMBH. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.