All RERA projects
๐๏ธ
Under construction
AKANKSHA CO. OP. HSG. SOC. LTD.
S.NO.48, H. NO.6(P), KULGAON, 421503
Dec 2026
Possession
43.6%
Built
0
Complaints
68
Units
Caution
- Behind schedule. Possession is due Dec 2026 but construction is only at 43.6%.
Official RERA facts
- Registration
- P51700076666
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 43.6% complete
- Units sold
- 10 of 68
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Jun 2024
- Floors
- 7
- Unit mix
- 66 res ยท 2 comm
- Architect
- PRAMOD V. PATIL & ASSOCIATES
Buyer community
Connect with other buyers and owners of AKANKSHA CO. OP. HSG. SOC. LTD. โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AKANKSHA CO. OP. HSG. SOC. LTD.. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.