Under construction

99 SILVER OAKS

by 99 SILVER OAKS

PLOT NO 30 , SECTOR 9, ULWE, Panvel, 410206

Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2031, now proposed Dec 2033 per the RERA filing.

Official RERA facts

Registration
P51700076739
Status
New
Stage
Certificate Signed
Possession
December 2033originally December 2031
Construction
9.1% complete
Units sold
0 of 108

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2024
Floors
16
Unit mix
102 res ยท 6 comm
Architect
HITEN SETHI & ASSOCIATES

Buyer community

Connect with other buyers and owners of 99 SILVER OAKS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 99 SILVER OAKS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.