PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Kasturi Vandana EmpireMahaRERA P51700077143

by Tirupati Estate Developers LLP

Survey No 118(old), 113(New), Hissa No,. 1, 2, 6 & 7, Narmada Nagar, 401105

Dec 2029
Possession
7%
Built
0
Complaints
0
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51700077143
Status
New
Stage
Certificate Signed
Possession
December 2029
Construction
7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2024
Floors
14

Buyer community

Connect with other buyers and owners of Kasturi Vandana Empire โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kasturi Vandana Empire. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.